On the resource sheet what does cost/use refer to in plain english?

RE: Microsoft Project

Simple, one-off costs only. If you have a deal with a car hire company for any car at


 

MS Project tip:

Avoid Accidental Constraints

The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)