ms project recurring

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » MS Project - Recurring Tasks

MS Project - Recurring Tasks

resolvedResolved · Urgent Priority · Version 2003

Diane has attended:
Project Introduction course
Project Introduction course

MS Project - Recurring Tasks

When inputting recurring tasks the task type is fixed units, however when adding resources the duration does not change, but it does when it is a task. Please explain. Thanks.

RE: MS Project - Recurring Tasks

Hi Diane

Thank you for your question

Simply put, the default setting for a normal task is for it to be "effort driven". This means that as additional resources are added, the duration of the task shortens. The effort driven setting overrides the effects of the task type

The default setting for recurring tasks is "not effort driven". This means that when you add resources, if the task type is fixed unit, the duration will remain the same and the total work will increase.


I hope this clarifies matters for you

Regards

Stephen


 

MS Project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.

View all MS Project hints and tips


Server loaded in 0.09 secs.