Resource Pool

resolvedResolved · Low Priority · Version 2007

Peter has attended:
Project Intro Intermediate course

Resource Pool

Will I experience any problems changing resource %ages on projects drawing from the resource pool, then levelling? What sort of things should I bear in mind, and what common pitfalls are there?

RE: Resource Pool

You will not be able to increase % allocation above the maximum level for resources shown in the pool but there should be no problems otherwise with changing percentages.

When levelling the pool however, there may be strange effects on work allocation - always check the hours allocated in Resource Usgae view!


 

MS Project tip:

Autofit column width – Project (all versions)

At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move.

A short bold vertical line will appear, with horizontal arrows pointing left and right.

Left click and hold this icon and it will permit you to grab the column line, allowing you to move it left or right to your desired location.

View all MS Project hints and tips


Server loaded in 0.08 secs.