Monitoring Progress
Resolved · Low Priority · Version Standard
Alix has attended:
Project Intro Intermediate course
Monitoring Progress
Is the main idea of MS Project that it is used just for planning projects, or is it perfectly acceptable to tweak the times it is ACTUALLY taking to complete tasks if your original estimates were not accurate?
RE: Monitoring Progress
Hi Alix
Thank You for your question
Project is as much a project tracking tool as it is a project planning tool, and it is very much acceptable to alter your actual times to reflect changes.
Once you have baselined the project, it is assumed that any changes you make reflect what is actually happening in the real world, and project will reflect in the tracking Gantt these changes and how they have affected the project's progress.
Regards
Stephen
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Format individual bars on your GANTT chartTo draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications. |