Change Working time - adding, deleting or renaming calendars

resolvedResolved · Low Priority · Version Standard

Steve has attended:
Project Intro Intermediate course

Change Working time - adding, deleting or renaming calendars

How do you delete or rename calendars once you have created new ones under the 'Change working time' button under 'Tools'?

RE: Change Working time - adding, deleting or renaming calendars

Hi Steve

Thankyou for your question. If you click on Tools-Organiser and select the calendars tab you will be given a complete list of the calendars in both the current project and the global tremplate.

You can then delete and rename the calendars as required. You can also copy calendars from the current project to the global template, thus making them available for all future projects created on that machine.

Hope this is useful

Regards

Stephen


 

MS Project tip:

Inserting Task Durations Quickly

When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.