Client Milestone

resolvedResolved · Urgent Priority · Version 2003

Antoine has attended:
No courses

Client Milestone

Hello, I would like to know how to change automatically my milestones into client milestones (Different shape and colour)

It works with the bars (Customize-Fields-Flag)+ adding in the bar style but whwn I do it with the milestones, nothing happens, it stays the some shape and colour of the normal milestone.

Have you got any ideas?

Many thanks

RE: Client Milestone

Hi Antoine

Thank you for your question.

There are two additional things you need to do once you have allocated your flag field and formatted the bar style

1. You need to change the bar style format so that the "from" and "to" fields in the bar styles dialog both say start.
2. For each client milestones you need to bring up the task details dialog and remove the "mark as milestone" tick on the advanced tab

This should then work

Regards

Stephen


 

MS Project tip:

Project Community

in the help menu type "Tips" then select "Ask the Project community" this takes you into microsofts site where you can ask questions to lots of knowledgeable people.They make up an online group of experienced Project users who answer questions and provide solutions and tips.

View all MS Project hints and tips