how do we set non working days on the calendar
Hi Christine
Thanks for your question.
From the menu choose Tools > change working time
In the dialogue box that appears click (or control click) to select the days to mark as non working and choose the Non-working time radio button.
I hope this helps - do let us know if you have any further questions.