Progress monitoring

resolvedResolved · High Priority · Version 2010

Paul has attended:
Project Intermediate course

Progress monitoring

Can we save a previous month progress to look back to what was previously recorded i.e. check movement within the month

RE: Progress monitoring

Hi Paul

Thanks for your question. I think it is related to saving baselines. But please can you give a bit more detail around your question so I can create an example and get back to you.

Thanks

Doug
STL


 

MS Project tip:

Autofit column width – Project (all versions)

At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move.

A short bold vertical line will appear, with horizontal arrows pointing left and right.

Left click and hold this icon and it will permit you to grab the column line, allowing you to move it left or right to your desired location.

View all MS Project hints and tips


Server loaded in 0.07 secs.