Recurring Tasks

resolvedResolved · Medium Priority · Version 2003

Joanne has attended:
Project Intro Intermediate course
Project Advanced course

Recurring Tasks

We are entering weekly meetings as a recurring task but it seems you have to add resources to each meeting week by week. Is there a way to allocate resources to a recurring task so they are linked to each event?

RE: Recurring Tasks

Hi Joanne

Thank you for your question - you would need to add the resources manually. The recurring task tool creates the events rather the assignments.

I'm sorry that I can't be of more help. Do let us know if you have any further questions.

Kind regards,
Andrew


 

MS Project tip:

MS Project 2010 Scroll to Task

Ever feel lost on a large project file? In Gantt view, Task ribbon, Editing, click on the Scroll to Task tool to centre the task bar on your screen.

Shortcut Ctrl+Shift+F5

Same as Go to Selected Task in MS Project 2003.