How does Risk and Issues relate to MS Project?
Hi Munira
Thank you for your question. MS Project doesn't have a dedicated Risk component. The Tracking Gantt view will show you the Critical path which may be of assistance. Project also contains spare fields such as Text1 which can be used to add your own custom data for your tasks.
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew
|
MS Project tip:Typing Links Between TasksIn the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between. |