Can you breakdown the cost elements for Resourcing to show
Hi Ann
Thank you for your question. In practice the figure for standard rate would probably be set to include additional costs such as insurance so that it represents the cost to the project of having this resource.
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew
Thu 6 Aug 2009: Automatically marked as resolved.
|
MS Project tip:Entering DaysTo type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date. |
We'll call during UK business hours
Server loaded in 0.08 secs.