Forum home » Delegate support and help forum » Microsoft Project Training and help » Resourcing
Resolved · Medium Priority · Version 2007
Chaitali has attended:
Project Intro Intermediate course
If you are unsure how much of a resources time will be available to you, I put in a percentage of the resource against each task, however this throuws questions at me and amends the units. is this the best way of assigning resources?
Hi Chaitali,
Thank you for your question and welcome to the forum.
I will have a look at your query tomorrow before we start training and then I will answer your question.
Regards
Simon
Hi Chaitali,
Thank you for your question and sorry for the delay in responding.
Have you found a way around your problem? Try the following:
If you go to Gantt chart view and use the window menu to split. In the bottom window choose the first resource from the left column and click OK.
Then edit either the unit or assign a particular amount of hours followed by OK again.
When you adjust the Unit the Hours will change and the same the other way round.
I hope this helps.
Regards
Simon
Mon 30 Nov 2009: Automatically marked as resolved.
|