Resourcing

resolvedResolved · Medium Priority · Version 2007

Chaitali has attended:
Project Intro Intermediate course

Resourcing

If you are unsure how much of a resources time will be available to you, I put in a percentage of the resource against each task, however this throuws questions at me and amends the units. is this the best way of assigning resources?

RE: Resourcing

Hi Chaitali,

Thank you for your question and welcome to the forum.

I will have a look at your query tomorrow before we start training and then I will answer your question.

Regards

Simon

RE: Resourcing

Hi Chaitali,

Thank you for your question and sorry for the delay in responding.

Have you found a way around your problem? Try the following:

If you go to Gantt chart view and use the window menu to split. In the bottom window choose the first resource from the left column and click OK.

Then edit either the unit or assign a particular amount of hours followed by OK again.

When you adjust the Unit the Hours will change and the same the other way round.

I hope this helps.

Regards

Simon

Mon 30 Nov 2009: Automatically marked as resolved.


 

MS Project tip:

Format individual bars on your GANTT chart

To draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications.