Forum home » Delegate support and help forum » Microsoft Project Training and help » ms project training london - Milestone
Resolved · Low Priority · Version Standard
carol has attended:
Project Introduction course
Project Intermediate course
How do I create a nwe milestone
Carol
Enter a zero 0 day in the duration part of the task
|
MS Project tip:Typing Links Between TasksIn the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between. |