course

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

TrustPilot

starstarstarstarstar Excellent

  • Home
  • Courses
  • Promotions
  • Schedule
  • Formats
  • Our Clients

Forum home » Delegate support and help forum » Microsoft Project Training and help » COURSE

COURSE

resolvedResolved · Medium Priority · Version 2007

Stephen has attended:
Project Intro Intermediate course

COURSE

cAN YOU PUT ME ON THE FORUM

RE: COURSE

Hello Stephen

Thank you for your post.

You now have 12 months access to our forum, to ask questions relating to the Project course you have attended with us.

Kind regards
Best Training

Wed 10 Dec 2008: Automatically marked as resolved.


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips


Server loaded in 0.08 secs.