Project 2013: Burndown charts help track work

what's new in office 2013Project 2013 comes with a brand new set of pre-designed reports and dashboards to help you better understand your data. You can visualise performance and analyse resources in ways that weren’t previously possible in Microsoft Project.

The burndown report is a much-requested feature that will be especially interesting to those of you practicing agile and Scrum-based methodology. Typically updated every day, this report is a common focal point of the daily scrum meeting.

Previously to see a burndown chart you had to employ some hacks and Excel templates to achieve the desired result. From Project 2013 it’s available as a standard report type.

Burndown charts in Project 2013

Select Report > Dashboard > Burndown

Burndown in Microsoft Project 2013

Usually the chart tracks work remaining (in time, effort points or quantity of tasks) against the date. One line represents how much work has been completed, a baseline of when to complete and the ‘perfect’ trajectory of task completion.

How is this chart useful?

Instead of tracking the amount of things done, the burndown chart reports on the amount of ‘effort’ or work left in the project phase. In other words you are ‘burning down’ the work. It will also predict based on current work rate whether the project will hit the target completion date. You’ll discover very soon whether the team is working at a fast enough rate. It’s great to get advance notice of how things are progressing and be able to adapt your project or adjust expectations sooner rather than later.

It can also be used to see whether a project team is over-performing and going to finish early. While this is usually good news this information can prove very useful in your next post-mortem. Do the team need to work on their task estimations? Or was the work completed to a less acceptable standard?

Find out more great advice like this with a Best STL course on Microsoft Project training London and UK wide.

Categories
Project Training

Using the Timeline feature in MS Project

The Timeline feature was first introduced to MS Project users in 2010. It helps to display a visual summary of a project. This post will detail the many functions of the Timeline feature and which benefits it can offer in addition to the normal Gantt view.

In its simplest form, the Timeline can be used to show the start and finish times of your project, allowing you to summarise tasks in line with the current date. You can also use the Timeline to pan through your project as a navigation pane.

Tasks can easily be added / removed from the Timeline or displayed as a callout above the navigation bar.  If it’s taking up too much room on the screen, the Timeline can be removed, displayed simply as bars without any detail text or as a single bar.

Getting Started: Displaying the Timeline

If it’s not already displayed: Select the View tab > Tick Timeline

Adding tasks to the Timeline

Making changes to the format of the Timeline is easy, simply click anywhere inside the Timeline to see the contextual Timeline Tools > Format ribbon.

To add tasks to the Timeline, click inside the Timeline then select Existing tasks.

Adding tasks to timeline in MS Project

Alternatively, right click a task in your project and choose Add to Timeline.

Adding each individual task can cause the Timeline to become cluttered. With this in mind, It makes sense not to add too many tasks. If you wish to add only the top level tasks select:

View > Outline > Level 1 > Highlight all the level 1 tasks > Right click and choose Add to Timeline. 

MS Project Timeline

Pan & Zoom

When the option Pan & Zoom is selected you can use the Timeline as a navigator for your project.

TL3

To pan to a different part of the timescale, drag the top edge of the square frame displayed in the Timeline to the left or right.

To zoom to a larger or smaller frame, click and drag the sides of the frame.

Overlapping Tasks

Turning off the option Overlapping tasks displays all the tasks in one single line.

Timeline in MS Project

Detailed Timeline

Turning off Detailed Timeline displays the Timeline as a series of bars without showing any task text.

Detailed Timeline in MS Project

Display as Callout

Rather than being displayed as bars, tasks can be displayed as Callouts above the Timescale. This can be used to highlight a group of tasks.  In this example the General Conditions phase is passed and displayed as a Callout.

Display as a callout

Date Format

The Date Format option within Timeline Tools allows the format of the Timescale dates to be changed (for example whether to include the year).  The Default option returns the Timescale to standard format.   The Show/Hide section at the bottom allows the Timescale, task dates and the current date to be hidden from view too.

Copy Timeline

Updating clients and colleagues with the progress of a project is an imperative aspect of the communication process. This option allows a Timeline to be copied into an email message or into a PowerPoint presentation slide for quick and easy sharing.

Copy a timeline

Switching Views

One of the benefits of The Timeline is that it remains on view when switching to other Project views such as Resource Sheet or Resource Usage views. This can help with managing and updating a project by reducing the need to keep switching views.  If it is not useful in a particular view then simply turn it off from the View tab.

In summary, the Timeline is a useful way of viewing and staying in control of top level tasks and communicating information to others. It also has the potential to help navigate and manage large projects.