project server training - project

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

TrustPilot

starstarstarstarstar Excellent

  • Home
  • Courses
  • Promotions
  • Schedule
  • Formats
  • Our Clients

Forum home » Delegate support and help forum » Microsoft Project Training and help » project server training - Project

project server training - Project

resolvedResolved · Low Priority · Version Standard

Lorna has attended:
Project Intro Intermediate course

Project

How do I cost my resources?

RE: Project

Hi Lorna

In the Resource sheet, when you create a new resource, you will find there is a cost field. Add a value here and this will be applied when you assign a resource to a task.

I hope this is helpful - do let us know if you have any further questions.

Kind regards,

Andrew


 

MS Project tip:

Autofit column width – Project (all versions)

At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move.

A short bold vertical line will appear, with horizontal arrows pointing left and right.

Left click and hold this icon and it will permit you to grab the column line, allowing you to move it left or right to your desired location.

View all MS Project hints and tips


Server loaded in 0.08 secs.