MS Project

How do I link tasks?

RE: MS Project

Hi Lucy,

In the Task Name field, select the tasks you want to link.
Click link Tasks button on the toolbar

Tracy


 

MS Project tip:

MS Project 2010 Scroll to Task

Ever feel lost on a large project file? In Gantt view, Task ribbon, Editing, click on the Scroll to Task tool to centre the task bar on your screen.

Shortcut Ctrl+Shift+F5

Same as Go to Selected Task in MS Project 2003.