How do I change the number of working hours within a day?
Thanks
Hi Claire
There are two things to consider here. First you need to set the times in your calendar, then ideally you need to make your units for a day match your calendar.
From the Tools menu choose change working time, select your working days and record the hours when work can take place. Then from the options button make sure your default start times / finish times and the hours per day match the settings you made in your calendar.
Hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew
|
MS Project tip:Giving Someone a Gantt Chart SnapshotTo pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010) |