ms project training course - project

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

TrustPilot

starstarstarstarstar Excellent

  • Home
  • Courses
  • Promotions
  • Schedule
  • Formats
  • Our Clients

Forum home » Delegate support and help forum » Microsoft Project Training and help » ms project training course - Project

ms project training course - Project

resolvedResolved · Low Priority · Version Standard

Dan has attended:
Project Intermediate course

Project

how do i change timescales

RE: project

Hi Dan

you can quickly format your timescale by double clicking it and then choosing one of the display options. Alternatively you can find the same dialog box by going to Format > Timescale

Hope this helps - do let us know if you need further assistance.

Kind regards,

Andrew


 

MS Project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)

View all MS Project hints and tips