scheduling tasks

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

TrustPilot

starstarstarstarstar Excellent

  • Home
  • Courses
  • Promotions
  • Schedule
  • Formats
  • Our Clients

Forum home » Delegate support and help forum » Microsoft Project Training and help » Scheduling tasks

Scheduling tasks

resolvedResolved · High Priority · Version 2013

Waqar has attended:
Project Introduction course

Scheduling tasks

I have set a task that must start on a specific date.

I have a number of tasks preceding the above task,

How do i make the preceding tasks schedule according to the task which i have set a constraint to/

I ham having trouble doing the above as the preceding tasks do not move and they have no constraints on them.

RE: scheduling tasks

Hi Waqar

Thanks for your question.

Project normally links tasks in a standard waterfall flow with 'Finish to Start' relationships between tasks.

If you want a task to start on a specific day then set a constraint. For example a dinner event.
Double click the task
Choose Advanced tab
Select the Constraint type Must start on.
Enter the start date for the event and press OK.

To make the other tasks finish on that specific event date create Start to Finish relationships for the other tasks.
Suppose the dinner event has an Id of 4.
Go to the the Predecessors column in the Gantt Chart and type 4SF for each task. (Can copy and paste or use the autofill handle).

Make sure all the tasks are set to Auto schedule.

I hope that helps. There are other approaches for example setting constraints to Finish Finish. That will work if the event is a milestone.

Regards
Doug
STL


 

MS Project tip:

Set default task type - Project 2010

a. In Project, click on the File tab
b. Select Options from left hand side
c. Click on Schedule to set the scheduling options
d. Set the Default Task type box to your chosen option
i. Generally if you plan/estimate your projects using durations you should use fixed duration, and untick the box New tasks are effort driven, if you plan/estimate with person hours use fixed work, or for plans estimated with the proportion of resources time use fixed units, and untick the box New tasks are effort driven)
e. Click OK to apply your changes

View all MS Project hints and tips


Server loaded in 0.07 secs.