how do I change a start date on my project?
Hi Jacob
Thank you for your question. You can change the project start date either by going to the Project menu, choosing Project information and setting the start date or by going to View > Toolbars > Analysis and from the toolbar that appears clicking on Analysis.
Make sure your plans have no recorded work in them before using either method.
Using adjust date will pick the plan in its entirety - including any float and position it on the date you choose. Changing the project start date may consume (or increase your float) if you have constraints in your plan.
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew
Fri 30 Oct 2009: Automatically marked as resolved.
|
MS Project tip:Avoid Accidental ConstraintsThe initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.) |