Earned Value Reporting

resolvedResolved · Low Priority · Version 2003

Tegwen has attended:
No courses

Earned Value Reporting

I am using MS Project 2007,but with excel 2003. I have done an earned value over time report and when I look the pivot table in Excel it does not show the same total as that of the project shown in MS Project? I have tried expanding the menus in the pivot table but this has not worked, what can I do to resolve this?

My projects budget is 1.5M but the pivot table shows 0.4M?

RE: Earned Value Reporting

Hi Tegwen

Thanks for your question!

Is it possible to send an example through for me to look at? You can email to info@stl-training.co.uk marking your message for my attention. In the meantime take a look at the built in earned value report by going to Report > Reports > Custom > Earned Value as well as using the built in tables to compare results.

Kind regards,
Andrew

RE: Earned Value Reporting

Tegwen,

I received your e-mail with attachments and I have forwarded the e-mail to Andrew.

Regards, Rich

RE: Earned Value Reporting

Hi Tegwen,

thanks for your question and for bearing with me. Some of the resources have no direct cost associated with them so would not directly generate earned value figures. As you pointed out their costs have been rolled up in costs elsewhere in the plan.

Do let us know if you have any further questions.

Kind regards,
Andrew


 

MS Project tip:

Create own ribbon tab - Project 2010

a. In Project click on the File tab
b. Select Options from left hand side
c. Choose the Customize Ribbon section
d. Click the New Tab button (below the list of tabs on the right hand side of the dialog box)
e. Select the New Tab (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
f. Select the New Group (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
g. Add commands to your tab and group by locating them on the list on the right hand side (remembering that you can change the list using the drop down box at the top of the list of commands) and clicking the Add button between the two panes to add them to your tab and group
h. You can rearrange the commands in your group, the groups on any tab or the tabs, using the up and down arrow buttons beside the list of tabs.
i. Click OK to apply your changes

View all MS Project hints and tips


Server loaded in 0.07 secs.