Adding milestones
Resolved · High Priority · Version 2007
Emma has attended:
Project Intro Intermediate course
Adding milestones
Hi
I am adding milestones to my plan and am entering a task with 0 days and then changing the start/finish date to reflect the date of the milestone. I keep getting a smart tag appear telling me this is not the best way to schedule a task.
Should I be entering the due date of the milestone in another way? Have read the project guide but it tells me to enter these via Advanced tab in Task Information Dialogue and says nothing regarding entering the date??
Thanks
RE: Adding milestones
Hi Emma
Thank you for your question.
Project is expecting you to add a constraint to the task. Double clicking on the task and switching to the Advanced tab allows you to set a constraint (EG start no earlier than) and set a date to position the task on the schedule.
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew
Mon 13 Apr 2009: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Format individual bars on your GANTT chartTo draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications. |