How do I specify a start date for a project
Hi Kio
Thank you for your question. When you are setting up your project you can use Project > Project information to set your project's start date.
If your planning is underway and you want to move your project forward you can use View > Toolbars > Analysis > Adjust dates to pick the project up and move it to a new date. This will preserve slack in your plan and move full constraint dates too.
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew
Tue 24 Mar 2009: Automatically marked as resolved.
|