Project Scheduling

resolvedResolved · Medium Priority · Version 2003

Haroon has attended:
Project Intro Intermediate course

Project Scheduling

How can a project calculate dates from Project finish date?

RE: Project Scheduling

Hi Haroon,

Thank you for your question.

When you create a project, you can set a Project Finish date instead of a Start Date. Once the tasks, durations and links have been completed, project applies an 'As Late As Possible' constraint to each task, thus generating the Project Start Date.

The Project Information screen can be found by accessing the Project menu and then Project Information.

I hope this answers your question.

Regards

Simon

Mon 12 Jan 2009: Automatically marked as resolved.


 